Fab towns / Boise, ID / Timeline

Where Micron Boise stands

Boise is the closest project to opening. The dates have moved earlier, not later, this year.

  • ID1. Micron’s guidance is first wafer output in mid-2027. Idaho News and a June 2026 Tradeline article both say it remains on track.
  • ID2. Expected in late 2028.
  • Construction. BoiseDev’s June 2026 aerial tour showed significant parts of the structure in place. One outlet reports equipment arriving in late 2026.
  • Earlier slips. Micron first said production would start in 2025, then 2026, and now 2027.
  • Money. Micron’s CHIPS Act funding of up to $6.4 billion covers two Idaho fabs, two New York fabs and a Virginia expansion.
Reports that progress is “ahead of schedule” come from secondary outlets. Micron’s own guidance is the mid-2027 date.