Mount Pleasant, Wisconsin

Project status: Mount Pleasant

Still building checked 1 Nov 2026

1building complete
2028building 2 due
15more approved
May 2024project announced

Where it stands

Status
Still building Phase 2
May 2024
Project announced.
Jan 2026
Village approved site plans for up to 15 more buildings.
23 Jun 2026
Building 1 complete and operating.
By 2028
Building 2 due.

What could change it

  • Each additional building needs its own investment decision.
  • Water and power concerns.
  • Microsoft's wider spending plans. In April 2025 it paused plans in Ohio.

Next check: weekly.