Cheyenne, Wyoming

Meta Cheyenne

Operating, expanding checked 1 Nov 2026

Read our full guide: town guide and status
152 MWpower online now
249 MWpeak planned or projected
$5.8Bestimated capital cost, built so far
WYWyoming

Facts

Owner
Meta
Main user
Meta
Chips
B300

Timeline

2024-04-01

Land clearing begins.

2025-01-30

Structure for Building 1 and 2 under construction.

2026-03-22

Building 1 shell and cooling looks complete, Building 2 roof almost complete.

2026-07-25

Both buildings estimated to be operational.

182 MW
2027-02-15 (projected)

Buildings 3 and 4 are similar in style and size to the ones seen at the Prometheus site, we estimate their operability based on that timeline.

249 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.