Cheyenne, Wyoming

Uncertain checked 1 Nov 2026

Cheyenne had the biggest announced project on this list, and it is also the least settled.

Status

  • Project Jade (Crusoe and Tallgrass): Laramie County approved a 1.8 GW campus in January 2026.
  • June 2026: Crusoe stopped work, saying it paused "at the request of our customer". Tallgrass said its own work continues and that Crusoe moved off the site.
  • Google: reported as the customer of a 2.7 GW campus on the site, with construction expected to finish by 2031.
  • Microsoft: has a separate Cheyenne campus. We did not confirm its current construction status.

We are waiting for the project to settle before writing a full guide.