San Antonio, Texas

Vantage TX1

Operating, expanding checked 1 Nov 2026

32 MWpower online now
179 MWpeak planned or projected
$1.2Bestimated capital cost, built so far
TXTexas

Facts

Chips
B200

Timeline

2023-12-15

Land clearing begins for both Building 1 & Building 2

2026-02-15

Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Although this is still earlier than the completion date reported on TDLR, based on the appearance, we believe it is operational. Reported IT power of 32 MW. [Source](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2024007561)

45 MW
2027-08-31 (projected)

Estimated construction completion date of Building 2. [Construction Project Filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026001234)

179 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.