Stream Phoenix
Operating, expanding checked 1 Nov 2026
Facts
- Chips
- H100
Timeline
Construction beginning, as can be seen on satellite. Major renovations on western side of the non AI building (PX1), including adding generators and cooling towers.
Major construction has finished on AI building 1, and AI building 6 has been expedited, as depicted by satellite imagery.
Estimated: AI building 1 should be operational. Major construction work finished by January 31, 2026, and the shell looked complete by that date. We estimate after three months the building will be operational.
77 MWAlthough official [promotional sources](https://www.streamdatacenters.com/wp-content/uploads/2026/01/SDC-Goodyear-CaseStudy-251218.pdf) estimate the campus to be fully operational in 10-12 years, it is likely to be finished sooner than this given the empirical durations for other data center campuses as well as because AI building 6 has been expedited. The first AI building took approximately 24 months to complete. Assuming construction for a new building starts midway for every building, then the campus will be complete in 4 years for the 5 remaining buildings, since AI buildings 2 and 6 are both underway.
267 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.