Manassas, Virginia

STACK Infrastructure NVA02

Operating, expanding checked 1 Nov 2026

85 MWpower online now
487 MWpeak planned or projected
$3.2Bestimated capital cost, built so far
VAVirginia

Facts

Chips
H100

Timeline

2019-10-19

Land clearing begins by Peterson Companies for Stack Infrastructure, which is noted in the [news](https://www.bisnow.com/washington-dc/news/data-center/peterson-cos-partnering-to-build-4m-sf-data-center-campus-in-manassas-102646) and visible on satellite imagery.

2024-10-01

Building 1 is operational, which is assumed to be three months after the last backup diesel generators are finished. The generators were first seen to be finished July 1 from satellite imagery [(a clear image of this can be seen on July 29 via Google Earth).](https://earth.google.com/web/search/38%c2%b044%2745%2e12%22N+77%c2%b032%2716%2e47%22W/@38.7458667,-77.5379083,83.89135729a,642.01325639d,35y,0h,0t,0r/data=CjQiJgokCTo0Rh9P7TVAETk0Rh9P7TXAGX6C6a6li0VAIQ_0AAa-ik7AKgYIARIAGAFCAggBQgIIAEoNCP___________wEQAA)

118 MW
2026-02-14

All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery.

118 MW
2028-01-01 (projected)

Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. One is complete, three are clearly under construction, and the last two data centers are still breaking ground and laying foundations.

487 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.