Eagle Mountain, Utah

QTS Eagle Mountain

Under construction checked 1 Nov 2026

0power online now
411 MWpeak planned or projected
n/aestimated capital cost, built so far
UTUtah

Facts

Owner
Meta
Main user
Meta

Timeline

2023-10-01

First signs of site preparation show up on satellite imagery.

2025-09-08

Site preparation continues. Outline of a first building that is not the data center of interest Buildings 1 or 2 is visible.

2026-05-02

Building 1 roof finished. Satellite imagery shows construction vehicles and concrete pads with no air cooled chiller units indicating Buildings 1 and 2 cooling install continues. On the other side of each building, emergency generator install continues as well.

2026-12-31 (projected)

We estimate Buildings 1 and 2 will be fully operational by the end of 2026 because there are at least seven months since cooling and emergency generators have started to be installed. This estimate is also in line with similar QTS data center campus construction timelines.

274 MW
2027-07-01 (projected)

We estimate Building 3 will be fully operational by H2 2027 following a similar time line to Buildings 1 and 2 of 14 months from land clearing to operational.

411 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.