Milam County, Texas

OpenAI Stargate Milam

Under construction checked 1 Nov 2026

0power online now
1.2 GWpeak planned or projected
n/aestimated capital cost, built so far
TXTexas

Facts

Owner
Softbank
Main user
OpenAI
Project
Stargate

Timeline

2025-09-27

Land clearing begins for the site

2026-01-04

Small sections of building foundation construction begins, and land clearing appears to be mostly finished

2026-03-23

Steel framing and roofing is underway for Building 1.

2028-12-31 (projected)

All buildings finished, site is fully operational. Our reasoning is that examples so far take a median of 2-2.5 years to go from land clearing to 1 GW. This suggests around 2028-01-01 here. However, due to delays being more likely than speedups and the fact that this base rate data is still unproven, the more conservative estimate is made. The current state of the site also supports this estimation.

1.2 GW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.