Saline Township, Michigan

OpenAI Stargate Michigan

Under construction checked 1 Nov 2026

0power online now
1.4 GWpeak planned or projected
n/aestimated capital cost, built so far
MIMichigan

Facts

Owner
Oracle
Main user
OpenAI
Project
Stargate

Timeline

2025-12-04

Land clearing begins for the entire site

2026-01-20

Land clearing continues for all buildings (1-3)

2026-03-12

Groundwork is visible for Building 1, at the left end of the site.

2028-12-31 (projected)

Buildings 1-3 operational. Based on when maximum power load will be provided by DTE energy (Dec 2027), which can be extended by a year. [Source, page 3](https://mi-psc.my.site.com/sfc/servlet.shepherd/version/download/068cs00001MH71XAAT)

1.4 GW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.