Lordstown, Ohio

OpenAI Stargate Lordstown

Under construction checked 1 Nov 2026

0power online now
300 MWpeak planned or projected
n/aestimated capital cost, built so far
OHOhio

Facts

Owner
Softbank
Main user
OpenAI
Project
Stargate

Timeline

2025-10-12

Land clearing begins in the front of the site (the side facing the Ohio Turnpike), clearing away a parking lot and solar array

2026-02-27

Still no visible construction, although construction within preexisting facilities

2026-07-30

Active construction visible on and around the datacenter, with the roofing mostly in place. This is based on satellite imagery. No buildings operational yet.

2027-03-01 (projected)

Projected operational date. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) Lordstown and Milam County could scale to 1.5 GW within 18 months of their September 23, 2025 announcement; subtracting Milam County's subsequently disclosed 1.2 GW capacity implies ~300 MW for Lordstown.

300 MW

Past entries are observations; entries marked projected are estimates and can change.