Microsoft SAT14
Operating checked 1 Nov 2026
Facts
- Owner
- Microsoft
- Chips
- H100, B300
Timeline
Land clearing for the site is almost complete. Informed using imagery on [Google Earth](https://earth.google.com/web/@29.476115,-98.68118,277.21295794a,724.52967601d,35y,0h,0t,0r/)
Building 1 operational. The first 2 data halls of Building 1 (with chillers already installed) are likely to be already operational. Although construction was completed prior, the on-site substation was previously incomplete, so we believe it was only operational at this point.
26 MWBuilding 2 chiller installation is a little more than halfway complete, and chiller installation for the last data hall of Building 1 is also around halfway complete.
26 MWNo more visible construction around either building, just a little equipment. Roads fully built around buildings as well.
26 MWBuilding 2 fully operational, Building 1 expanded. Construction is already visibly complete. Additionally, construction phases [Phase 2](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2021019471), [Phase 3](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2021019588), and [Phase 4](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2021019686) on TDLR that collectively represent the completion of the site have a completion date of 2026-03-31.
66 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.