Cumming, Iowa

Microsoft Project Osmium

Operating checked 1 Nov 2026

190 MWpower online now
190 MWpeak planned or projected
$7.2Bestimated capital cost, built so far
IAIowa

Facts

Owner
Microsoft
Main user
OpenAI
Chips
A100, H100, B200

Timeline

2018-12-18

Land clearing begins on the north part of the site

2021-01-01

Building 1 and 1st building on the site are operational. Foundation work begins on Building 2

57 MW
2023-06-30

Building 2 is operational. Estimated based on Microsoft H100 count 2023

114 MW
2025-03-01

Building 3-4 operational, no visible construction.

228 MW
2025-10-08

Site already complete.

228 MW
2026-06-16

No notable changes since October.

228 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.