Vineland, New Jersey

Microsoft-Nebius New Jersey

Operating checked 1 Nov 2026

50 MWpower online now
50 MWpeak planned or projected
$1.9Bestimated capital cost, built so far
NJNew Jersey

Facts

Owner
Nebius
Main user
Microsoft
Chips
B300

Timeline

2024-05-31

Land clearing begins for northern two buildings (Building 1-2).

2025-12-15

By mid-December 2025 the building was still not complete. A satellite analysis by SemiAnalysis found that the air-cooled chillers serving the second half of the first 50 MW phase were not yet installed, so the phase was not yet operational. SemiAnalysis estimated the full 50 MW would be reached around January to February 2026.

2026-04-15

High-resolution satellite imagery shows the air-cooled chiller array has grown to roughly 30 units, enough to support the first phase. We estimate Building 1 became operational around early 2026 with about 50 MW of IT capacity (70 MW total facility power at a 1.4 PUE), based on DataOne's disclosure of a first 50 MW phase. SemiAnalysis estimated the full 50 MW was reached around January to February 2026 ([SemiAnalysis](https://newsletter.semianalysis.com/p/stop-saying-half-of-2026-us-datacenter)); this April image is our first high-resolution confirmation that the cooling is in place.

70 MW
2026-07-12

Compared with the April 2026 image, the building shell is closer to completion, and several additional air-cooled chillers have appeared on the ground, though they do not yet appear to be connected or operating. We therefore keep IT capacity at 50 MW.

70 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.