Goodyear, Arizona

Microsoft Goodyear

Operating checked 1 Nov 2026

202 MWpower online now
202 MWpeak planned or projected
$7.7Bestimated capital cost, built so far
AZArizona

Facts

Owner
Microsoft
Main user
OpenAI, Microsoft
Chips
H100, B200

Timeline

2021-06-21

Land clearing begins for Building 1.

2023-04-24

Building 1 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

53 MW
2025-01-16

Building 2 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

105 MW
2025-09-01

Building 3 and 4 operational. Based on interpolating satellite images from Sentinel-2 and Google Earth.

263 MW
2025-11-12

Confirmation that Building 3 and 4 look complete.

263 MW
2026-04-27

Foundations appear to be underway for Building 5 and 6, just north of Building 4.

263 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.