Meta Temple
Operating checked 1 Nov 2026
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
- Builders
- JE Dunn
Timeline
Land clearing begins.
A traditional H-shaped Meta data center is partially built.
The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.
Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.
Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2022017728) is 2026-03-01.
198 MWBuilding 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.
198 MWBuilding 3 is operational. Based on the stated completion date in this [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008019)
231 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.