Rosemount, Minnesota
Meta Rosemount
Operating checked 1 Nov 2026
178 MWpower online now
178 MWpeak planned or projected
$6.7Bestimated capital cost, built so far
MNMinnesota
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B200
Timeline
2024-05-01
Land clearing begins.
2026-03-21
Both buildings and their cooling infrastructure look complete, but the site probably is likely still under commissioning, and few cars are parked to the right of Building 1. We give another 3 months before it's operational.
2026-06-19
Buildings 1 and 2 are estimated to be operational.
241 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.