Meta Montgomery
Operating, expanding checked 1 Nov 2026
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
- Builders
- Hensel Phelps
Timeline
Land clearing begins.
Building 1 and 2 under construction, with all chillers visible.
Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site and few cars in the front carpark, so we expect 3 more months needed for commissioning and server installation. Building 3 has a half-finished roof and Building 4 shell is beginning construction. Buildings 5 and 6 are under construction.
We estimate Buildings 1 and 2 are operational.
199 MWBuildings 5 and 6 are operational (estimate). Based on the tent buildings at Meta Prometheus taking about 12 months from starting the tent structure to estimated operation.
266 MWBuildings 3 and 4 are operational (estimate). In September 2025, Building 1 and 2 appeared to be in a similar state to Building 3 and 4 in May 2026. Based on that, we apply an 8-month delay to the Building 1 and 2 operational date to get the Building 3 and 4 operational date.
465 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.