Los Lunas, New Mexico

Meta Los Lunas

Operating, expanding checked 1 Nov 2026

118 MWpower online now
273 MWpeak planned or projected
$4.5Bestimated capital cost, built so far
NMNew Mexico

Facts

Owner
Meta
Main user
Meta
Chips
B300

Timeline

2024-07-24

Land clearing starts for new building.

2026-03-01

Building 1 is operational, based on no construction activity around the shell and cooling equipment, and about 5 months passing after structural completion.

114 MW
2026-07-28

Building 2 (a tent-like building) shell is complete, but we don't believe it's operational because there is unpaved ground, no cars parked right in front, the first tent buildings at Meta Prometheus took about 16 months (it's been 10 months for this building). North-west of Building 1, the outline of a building of similar dimensions and style to Meta Jeffersonville's Building 1 is visible, this is labeled as Building 3. West of Building 1 we see more land clearing for what could be a building similar to Meta Jeffersonville's Building 2.

114 MW
2026-10-26

Building 2 (a tent like building) is operational. Based on a default estimate of 3 months for fit-out after structural completion in July.

147 MW
2028-01-01 (projected)

Building 3 is estimated to be operational. This is estimated from the timeline of similar buildings at other Meta sites.

273 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.