Jeffersonville, Indiana
Meta Jeffersonville
Operating checked 1 Nov 2026
178 MWpower online now
178 MWpeak planned or projected
$6.7Bestimated capital cost, built so far
INIndiana
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
Timeline
2024-02-01
Land clearing begins.
2026-03-06
Building 1 and 2 shell and cooling look complete, but there's still construction activity. We give it another 3 months to operational.
2026-06-04
Building 1 and 2 are operational.
241 MWPast entries are observations; entries marked projected are estimates and can change.