Gallatin, Tennessee
Meta Gallatin
Operating checked 1 Nov 2026
87 MWpower online now
87 MWpeak planned or projected
$3.3Bestimated capital cost, built so far
TNTennessee
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
Timeline
2023-09-11
Land clearing starts for Building 1.
2026-02-09
Building 1 shell and cooling looks complete, but construction equipment is still seen around cooling and building.
2026-08-24
Building 1 is operational, based on a lack of construction activity around the shell and cooling equipment, and about 6 months passing after structural completion.
114 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.