Eagle Mountain, Utah

Meta Eagle Mountain

Operating checked 1 Nov 2026

133 MWpower online now
133 MWpeak planned or projected
$5.0Bestimated capital cost, built so far
UTUtah

Facts

Owner
Meta
Main user
Meta
Chips
B300
Builders
Mortenson
Power suppliers
Williams

Timeline

2023-10-01

Land clearing begins.

2025-09-08

We believe Buildings 1 and 2 are still undergoing testing due to construction equipment and unfinished land surrounding the data center sites, as well as color motion artifacts on a small number of the cooling fans.

2025-12-07

Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.

179 MW
2026-05-02

Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.

179 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.