Eagle Mountain, Utah
Meta Eagle Mountain
Operating checked 1 Nov 2026
133 MWpower online now
133 MWpeak planned or projected
$5.0Bestimated capital cost, built so far
UTUtah
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
- Builders
- Mortenson
- Power suppliers
- Williams
Timeline
2023-10-01
Land clearing begins.
2025-09-08
We believe Buildings 1 and 2 are still undergoing testing due to construction equipment and unfinished land surrounding the data center sites, as well as color motion artifacts on a small number of the cooling fans.
2025-12-07
Buildings 1 and 2 both estimated to be operational 90 days after testing was underway in September.
179 MW2026-05-02
Satellite image shows strong evidence that Buildings 1 and 2 are operational: colored motion artifacts on many cooling fans, plus cars parked at the building entrances.
179 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.