Trenton, South Carolina
Meta Aiken
Operating, expanding checked 1 Nov 2026
69 MWpower online now
168 MWpeak planned or projected
$2.6Bestimated capital cost, built so far
SCSouth Carolina
Facts
- Owner
- Meta
- Main user
- Meta
- Chips
- B300
Timeline
2024-05-30
Land clearing begins
2026-04-08
Buildings 1 and 2 are nearly complete, but there's still some equipment strewn around the site. We expect around 3 more months needed for commissioning and server installation.
2026-08-07
Building 1 is confirmed operational via drone imagery with 8/9 group of coolers with spinning fans. Imagery also confirms all cooling and power infrastructure in place for Building 2.
90 MW2026-11-05 (projected)
Building 2 is operational assuming a 3 month lag compared to Building 1.
168 MWPast entries are observations; entries marked projected are estimates and can change.