The Dalles, Oregon
Google The Dalles
Operating checked 1 Nov 2026
154 MWpower online now
154 MWpeak planned or projected
$5.8Bestimated capital cost, built so far
OROregon
Facts
- Owner
- Chips
- TPU v6e, TPU v5p, TPU v5e, TPU v7
Timeline
2023-05-21
First signs of construction.
2025-03-07
Building 1 is estimated to be operational, based on all external equipment being installed.
93 MW2026-04-29
Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.
185 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.