Google Pryor (North)
Operating checked 1 Nov 2026
Facts
- Owner
- Main user
- Google DeepMind
- Chips
- TPU v5p, TPU v5e
Timeline
Building 1 is operational, based on default roof-to-operational time.
63 MWBuilding 2 is being retrofitted from a warehouse. The roof is being painted white, and cooling towers and a new substation are being built just south of the building (based on later imagery).
63 MWThe new substation for Building 2 looks mostly complete, half of the cooling towers are installed. The black patch in the top left of the building suggests that the new roof is not quite complete.
63 MWBuilding 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.
63 MWBuilding 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.
442 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.