Pryor, Oklahoma

Google Pryor (North)

Operating checked 1 Nov 2026

368 MWpower online now
368 MWpeak planned or projected
$13.9Bestimated capital cost, built so far
OKOklahoma

Facts

Owner
Google
Main user
Google DeepMind
Chips
TPU v5p, TPU v5e

Timeline

2024-07-19

Building 1 is operational, based on default roof-to-operational time.

63 MW
2025-01-28

Building 2 is being retrofitted from a warehouse. The roof is being painted white, and cooling towers and a new substation are being built just south of the building (based on later imagery).

63 MW
2025-10-19

The new substation for Building 2 looks mostly complete, half of the cooling towers are installed. The black patch in the top left of the building suggests that the new roof is not quite complete.

63 MW
2026-05-26

Building 2 looks almost complete, but still appears to have three cooling towers missing. We therefore expect another 3 months until full operation.

63 MW
2026-09-06

Building 2 is operational, confirmed via RAAD drone imagery of spinning cooling tower fans on September 8th.

442 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.