Omaha, Nebraska

Google Omaha

Operating, expanding checked 1 Nov 2026

237 MWpower online now
474 MWpeak planned or projected
$9.0Bestimated capital cost, built so far
NENebraska

Facts

Owner
Google
Main user
Google DeepMind
Chips
TPU v5e, TPU v5p, TPU v6e, TPU v7

Timeline

2021-11-25

Land clearing begins.

2024-04-08

Building 1 operational, based on it being 6 months after roof was complete, infrastructure looked complete for 5 months.

95 MW
2024-07-29

Building 2 has 3 cooling towers installed.

95 MW
2024-11-19

Building 2 is operational, based on it being 8 months since the roof was complete, and surrounding infrastructure looks just completed (finishing the cooling towers).

189 MW
2025-03-16

Confirmation that there's no obvious construction happening for Building 2. Building 3 roof started.

189 MW
2025-04-21

Confident that Building 2 is operational

189 MW
2025-10-21

Building 3 has all backup generators in place but they are still being installed. Two cooling towers have fans on them, with more underway. To the south of Building 3, more land has been cleared and there's a new carpark. This suggests another building will soon start construction.

189 MW
2026-05-15

Building 3 appears almost complete, with only minimal construction work and equipment remaining. The cooling towers are spaced apart in an unusual way, but there's no obvious sign that more will be installed before operation. Buildings 4 and 5 haven't started construction yet, the cleared land is still empty.

189 MW
2026-06-30

Building 3 is operational (estimate). Based on there being minimal construction work as of May 15.

284 MW
2028-01-23 (projected)

Building 4 is operational. Expect a 4th building because there's enough land cleared for it. Assuming the foundation starts at the end of May 2026 and it takes a similar time to Building 3 from foundation to operational (1 year 8 months).

379 MW
2028-07-23 (projected)

Building 5 is operational. We expect a 5th building because there's enough land cleared for one. We assume a roughly 6-month delay after Building 4.

474 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.