Lincoln, Nebraska

Google Lincoln

Operating, expanding checked 1 Nov 2026

141 MWpower online now
339 MWpeak planned or projected
$5.3Bestimated capital cost, built so far
NENebraska

Facts

Owner
Google
Chips
TPU v6e, TPU v7

Timeline

2023-07-01

Land clearing begins for the site

2025-10-23

Building 1 looks mostly complete: the large items like generators and substation are done. It is just missing 2 more cooling towers (4 fans). They just seem to be paving and setting up the secondary equipment so it is probably a few months away from operation. Building 2 foundation has been laid.

2026-05-12

Building 1 operational. This is based on the fact that is no more visible equipment or construction around the building, and based on previous imagery and when construction started on the last pieces of equipment (fans). Building 2's roof is complete, with generator construction more than halfway complete and cooling construction beginning. Electrical equipment on the side of Building 2 is also around halfway complete.

170 MW
2027-10-01 (projected)

Building 2 operational. Estimated based on the construction timeline for Building 1, specifically the time to operational since the roof was complete and the time to operational since the foundation work began.

339 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.