Kansas City, Missouri

Google Kansas City East

Operating checked 1 Nov 2026

105 MWpower online now
105 MWpeak planned or projected
$4.0Bestimated capital cost, built so far
MOMissouri

Facts

Owner
Google

Timeline

2024-01-01

Land clearing has begun for the site

2024-03-01

Foundation work begins on Building 1

2024-10-01

Foundation work begins on Building 2. Building 1 roof is fully black.

2025-07-01

Foundation work begins for Building 3. Building 1 generators seem complete.

2025-11-01

Foundation work begins for Building 4. Building 2 roof is almost complete, and construction appears to have started on cooling. Building 1 cooling construction continues, and the substation right next to it seems finished as well.

2026-04-16

Building 1 is almost complete, with only cooling needing 4 more fans. Building 2 backup generator construction has begun, and cooling tower installation is about halfway complete. Building 3's roof is almost complete, and construction has started on generators and cooling. A clear foundation has been cleared for Building 4, though no construction has begun.

2026-08-01

Building 1 operational. Estimated based on present construction progress and typical timelines.

126 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.