Google Council Bluffs (East)
Operating checked 1 Nov 2026
Facts
- Owner
- Main user
- Google DeepMind
- Chips
- TPU v5e, TPU v6e, TPU v5p, TPU v7
Timeline
Land clearing begins for east buildings
Building 1 is operational. Google Earth shows Building 1 had all backup generators and cooling towers installed by the end of August, but construction work was ongoing and there were almost no cars parked. By February 2025, Google Earth shows no construction work and many cars. So our best guess is in the middle, in November 2024. Building 3 roof is complete.
95 MWBuilding 2 is operational. Assuming it takes 3 months after generators and cooling towers are finished, similar to Building 1.
190 MWLand clearing begins in the southwest, suggesting more buildings are planned.
190 MWBuilding 3 has all 34 backup generators installed and 4 cooling towers installed, with 3 more cooling towers under construction. There are gaps between cooling towers suggesting that more could be added. Buildings 1 and 2 are running close to full capacity, given that water vapor is coming out of 5 of 7 cooling towers for each building. The land cleared in the southwest appears to be shaped for two more similar buildings, with notches for substations.
190 MWBuilding 3 is operational. 7 cooling towers were finally installed despite being more spread out compared to the first two buildings. Cooling towers models vary slightly between buildings. Ground clearing to the southwest seems to be setting up for two more buildings.
284 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.