Google Cedar Rapids
Under construction checked 1 Nov 2026
Facts
- Owner
- Main user
- Google DeepMind
Timeline
Land clearing begins.
Building 1 cooling towers and generators starting to be put in place. There's a foundation for Building 2 and 3.
About half of Building 1 generators are in place. Building 2 roofing has started - about where Google Omaha Building 3 was on 2025-03-16.
Building 1's generators are still only about halfway in place, and ~1/2 the cooling towers are still under construction. Building 2 roofing has been completed, and visible foundations have been built for cooling towers and generators.
Building 1 is operational. There is still work to be done since April, and Q4 2026 operational estimate was based on visible progress then.
105 MWBuilding 2 is operational. Based on Google Omaha Building 3 taking about 14 months from starting the roof to operation.
209 MWBuilding 3 is operational. Earlier satellite images suggest it was about 3 months behind Building 2.
314 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.