Bristow, Virginia
Google Bristow
Operating checked 1 Nov 2026
238 MWpower online now
238 MWpeak planned or projected
$9.0Bestimated capital cost, built so far
VAVirginia
Facts
- Owner
- Main user
- Google DeepMind
- Chips
- TPU v5e, TPU v5p, TPU v6e, TPU v7
Timeline
2021-07-01
Land clearing begins.
2024-04-29
Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.
104 MW2025-04-29
Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.
208 MW2026-05-20
Building 3 is operational, based off of colored motion artifacts from cooling towers.
286 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.