Bristow, Virginia

Google Bristow

Operating checked 1 Nov 2026

238 MWpower online now
238 MWpeak planned or projected
$9.0Bestimated capital cost, built so far
VAVirginia

Facts

Owner
Google
Main user
Google DeepMind
Chips
TPU v5e, TPU v5p, TPU v6e, TPU v7

Timeline

2021-07-01

Land clearing begins.

2024-04-29

Building 1 is operational, based off of colored motion artifacts from cooling towers. Building 2 is undergoing construction.

104 MW
2025-04-29

Building 2 is operational, based off it being at least 12 months since the roof was complete. Building 3 is finishing construction of cooling towers.

208 MW
2026-05-20

Building 3 is operational, based off of colored motion artifacts from cooling towers.

286 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.