Sterling, Virginia
Google Arcola
Operating checked 1 Nov 2026
77 MWpower online now
77 MWpeak planned or projected
$2.9Bestimated capital cost, built so far
VAVirginia
Facts
- Owner
- Chips
- TPU v6e, TPU v7
Timeline
2024-10-01
Building 1 foundation started
2025-09-08
Building 1 roof complete, cooling towers in progress.
2026-04-09
Building 1 appears almost complete, with minimal construction activity.
2026-06-16
Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification.
93 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.