Claude, Texas

Goodnight

Under construction checked 1 Nov 2026

0power online now
1.3 GWpeak planned or projected
n/aestimated capital cost, built so far
TXTexas

Facts

Owner
Google
Main user
Google DeepMind
Builders
Crusoe, Hoffman
Power suppliers
Serena

Timeline

2025-05-19

Land clearing begins

2025-10-16

Building 1 and 2 under construction.

2025-12-23

Construction on Building 1 and 2 looks about halfway to completion. Foundations and utility trenches are visible for Building 3-4. Building 5-6 have an outline. The substation appears to be expanding.

2026-04-16

Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. The substation expansion seems to be nearing completion.

2027-03-15 (projected)

Building 1 operational. This [regulatory document](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2025027064) lists the completion date for Building 1 as 2026-09-12, the current status suggests this estimate will not be met. Based on the timeline seen at the Abilene,Texas site for the same building styles and the most recent imaged status, we estimate operability to occur 6 months after the state seen in Sept 2026.

132 MW
2027-05-15 (projected)

Building 2 operational. The completion date for [Building 2 Tenant Improvement](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2025027065) is 2026-11-07, about 2 months later than Building 1. We therefore add 2 months to the Building 1 operational date.

265 MW
2027-10-01 (projected)

6 buildings are operational. This is based on: 1. A [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026010861) for Building 6 with a completion date of 2027-07-30. Normally there is a follow-up filing for "tenant improvement" which involves building the interior, with a completion date 1-3 months after the initial filing. 2. A project deadline of EOY 2027 in the [original tax abatement agreement](https://www.co.armstrong.tx.us/upload/page/5361/Phase%201%20Tax%20Abatement%20Agreement%20-%20Signed.pdf) 3. The similar 8-building project in Abilene taking an estimated 2 years and 2 months.

1.3 GW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.