Abilene, Texas
Crusoe Abilene Expansion
Under construction checked 1 Nov 2026
Read our full guide: town guide and status
0power online now
941 MWpeak planned or projected
n/aestimated capital cost, built so far
TXTexas
Facts
- Owner
- Microsoft
- Main user
- Microsoft
- Investors
- NVIDIA
Timeline
2025-11-02
Land clearing begins for Buildings 1-2.
2026-01-15
Land clearing continues.
2027-09-17 (projected)
Building 1 operational. Based on the completion date to "build-out an office and data hall", stated in a [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008308).
470 MW2027-11-11 (projected)
Building 2 operational. Based on the completion date to "build-out an office and data hall", stated in a [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008308).
941 MWPast entries are observations; entries marked projected are estimates and can change.
Sources (checked 1 Nov 2026)
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.