Abilene, Texas

Crusoe Abilene Expansion

Under construction checked 1 Nov 2026

Read our full guide: town guide and status
0power online now
941 MWpeak planned or projected
n/aestimated capital cost, built so far
TXTexas

Facts

Owner
Microsoft
Main user
Microsoft
Investors
NVIDIA

Timeline

2025-11-02

Land clearing begins for Buildings 1-2.

2026-01-15

Land clearing continues.

2027-09-17 (projected)

Building 1 operational. Based on the completion date to "build-out an office and data hall", stated in a [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008308).

470 MW
2027-11-11 (projected)

Building 2 operational. Based on the completion date to "build-out an office and data hall", stated in a [regulatory filing](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2026008308).

941 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.