CoreWeave Muskogee OK
Under construction checked 1 Nov 2026
Facts
- Owner
- CoreWeave
- Main user
- OpenAI
Timeline
Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center. Core Scientific [says](https://investors.corescientific.com/news-events/press-releases/detail/99/core-scientific-and-port-muskogee-break-ground-on-100-mw-hpc-data-center) the site will provide about 70 MW of critical IT load for CoreWeave's NVIDIA GPUs.
Based on satellite imagery, Building 1 looks mostly complete, but the site still appears to be in construction or commissioning. Not much progress has happened in the past 4 months, and a Q2 2026 finish seems unlikely.
Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators. We can assume Building 1 is not operational from all the yard work directly surrounding it, and the lack of a parking lot. Building 2 (The one not leased to CoreWeave) is still in land clearing phase.
Estimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will likely still take several months, judging from the slow pace.
98 MWCore Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.sec.gov/Archives/edgar/data/1839341/000162828026030918/exhibit991polarispressre.htm
181 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.