Marble, North Carolina

CoreWeave Marble NC

Operating checked 1 Nov 2026

65 MWpower online now
65 MWpeak planned or projected
$2.5Bestimated capital cost, built so far
NCNorth Carolina

Facts

Owner
CoreWeave
Main user
OpenAI
Chips
B200

Timeline

2024-06-25

Core Scientific announced that CoreWeave would receive about 70 MW of HPC infrastructure from 100 MW of owned infrastructure. Site modifications were expected to begin in H2 2024.

2026-03-13

The site has been energized. Two of three data halls had been delivered at [37 billable MW](https://www.sec.gov/Archives/edgar/data/1839341/000119312526165121/d149019dex992.htm), supporting about 15000 Grace Blackwell GPUs. The third hall was still in commissioning.

50 MW
2026-04-17

Satellite imagery shows the main data hall and southern utility yard substantially complete. No new public MW disclosure, so this keeps the March 2026 public 36 MW state.

50 MW
2026-05-06

Core Scientific said Marble was fully handed over to CoreWeave with about 65 MW of billable customer power online.

91 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.