CoreWeave Denton TX
Operating, expanding checked 1 Nov 2026
Facts
- Owner
- CoreWeave
- Main user
- OpenAI
- Chips
- B200
Timeline
Construction start - The [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/TABS/Search/Print/TABS2025005706) reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.
First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025corescientificinc-ea.htm), with another 40 scheduled by the end of the quarter.
11 MWHalf the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY25+earnings+deck+vfinal.2+PDF.pdf) to CoreWeave's GPUs across three buildings.
94 MWBuildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.
183 MWBuildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an [earnings call](https://www.fool.com/earnings/call-transcripts/2026/03/02/core-scientific-corz-q4-2025-earnings-transcript/) from this date.
183 MWBuildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1066/11282/pdf/Q2+FY26+earnings+deck+7.28+AM.pdf) stating the campus was operational by midyear 2026.
367 MWBuilding 8 interior fit-out scheduled to begin. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
367 MWBuilding 8 projected operational. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules Building A's data-hall fit-out for completion by this date.
395 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.