Denton, Texas

CoreWeave Denton TX

Operating, expanding checked 1 Nov 2026

262 MWpower online now
395 MWpeak planned or projected
$9.9Bestimated capital cost, built so far
TXTexas

Facts

Owner
CoreWeave
Main user
OpenAI
Chips
B200

Timeline

2024-11-01

Construction start - The [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/TABS/Search/Print/TABS2025005706) reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.

2025-05-31

First 8 MW billable tranche dedicated to AI [starts running at the site](https://investors.corescientific.com/sec-filings/all-sec-filings/content/0001628280-25-023161/q12025corescientificinc-ea.htm), with another 40 scheduled by the end of the quarter.

11 MW
2025-12-31

Half the campus energized. 67 billable MW [are now dedicated](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1085/11265/presentation/Q4+FY25+earnings+deck+vfinal.2+PDF.pdf) to CoreWeave's GPUs across three buildings.

94 MW
2026-02-23

Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.

183 MW
2026-03-02

Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an [earnings call](https://www.fool.com/earnings/call-transcripts/2026/03/02/core-scientific-corz-q4-2025-earnings-transcript/) from this date.

183 MW
2026-07-03

Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the [Q2 2026 Earnings call](https://d1io3yog0oux5.cloudfront.net/_68280da94b2098ec46fcbe3f4628ea40/corescientific/db/1066/11282/pdf/Q2+FY26+earnings+deck+7.28+AM.pdf) stating the campus was operational by midyear 2026.

367 MW
2026-09-01

Building 8 interior fit-out scheduled to begin. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.

367 MW
2027-05-31 (projected)

Building 8 projected operational. [TDLR project TABS2026028247](https://www.tdlr.texas.gov/TABS/Projects/TABS2026028247) schedules Building A's data-hall fit-out for completion by this date.

395 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.