CoreWeave Chester VA
Operating, expanding checked 1 Nov 2026
Facts
- Owner
- CoreWeave
- Main user
- OpenAI
- Chips
- H100, B200
Timeline
Conversion starts at CTP-01 (Building 1). The data center was formerly owned by Capital One, now leased to CoreWeave. Source: https://www.datacenterdynamics.com/en/news/chirisa-secures-200-million-loan-to-fit-out-virginia-data-center-for-coreweave/
Building 1's second data hall scheduled to come online this month.
25 MWBuilding 1 is scheduled to be fully online by this point, so we count the full 27 MW as operational here.
38 MWSatellite imagery shows Building 1 complete, with Building 2's yard work and early construction visible. Building 3 hasn't started yet, since the old building is still there.
38 MWBased on satellite imagery, Building 3 has cleared its land and is beginning construction. Building 2 is operational judging from the colored motion artifacts on the cooling tower fans.
114 MWBuildings 3 is estimated complete by the end of Q1 2027, based on the current PowerHouse schedule. Added another three months to account for commissioning and server installation.
197 MWPast entries are observations; entries marked projected are estimates and can change.
Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.