New Albany, Ohio

AWS New Albany

Operating, expanding checked 1 Nov 2026

Read our full guide: town guide and status
213 MWpower online now
405 MWpeak planned or projected
$8.1Bestimated capital cost, built so far
OHOhio

Facts

Owner
Amazon
Chips
Trainium2, H100, H200, B200

Timeline

2022-07-01

Land clearing begins for Buildings 5-9 (eastern campus).

2024-12-01

Buildings 5-9 (eastern campus) operational. [New Albany’s Dec. 2024 report](https://newalbanyohio.org/wp-content/uploads/2025/01/CD-2024-12.pdf) lists AWS partial occupancy for 5 buildings at the eastern campus. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html). The full IT power is much higher than 113 MW.

136 MW
2026-03-12

Middle campus Buildings 10, 12, 13, and 14 appear complete/likely operational. Building 11 is still installing backup generators, so it is not counted as operational. Based on satellite imagery, northern campus Buildings 1-3 appear in late construction, with all roofs complete but nearby generator/cooling equipment still being installed for buildings 2-3. Building 4 is still early in construction. Eastern campus Buildings 5-9 appear complete and operational as expected. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html).

255 MW
2026-05-18

Satellite imagery shows Building 1 in the northern campus still appears structurally finished, with no visible change from the prior two months, but we're still not counting it operational due to visible construction work around the perimeter. Buildings 2-3 still have nearby generators/cooling equipment being installed, and Building 4 is only roughly 80% roofed. Eastern campus Buildings 5-9 remain operational. Middle campus Buildings 10, 12, 13, and 14 remain operational; Building 11 is still installing backup generators and is not counted.

255 MW
2027-07-01 (projected)

Expected operational date for the remaining tracked buildings (11, and 1-4) across the three campuses. This estimate is based on the previous buildings taking roughly 1.5 years from steel framing to complete operational status. Note that we're only including roughly 44% of all the New Albany campuses IT Power as being dedicated to leading AI chips, based on all the types of compute instances [listed](https://docs.aws.amazon.com/ec2/latest/instancetypes/ec2-instance-regions.html).

405 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.