Barker, New York

Anthropic Lake Mariner

Operating, expanding checked 1 Nov 2026

210 MWpower online now
441 MWpeak planned or projected
$8.0Bestimated capital cost, built so far
NYNew York

Facts

Owner
AI XPV Platform
Main user
Anthropic
Chips
TPU v7
Investors
Google, Blackstone

Timeline

2025-06-11

Land clearing begins for Building 1 (AKA CB3).

2026-03-02

Building 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation.

2026-05-31

Building 1 is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from [RAAD](https://raad.com/) shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.

49 MW
2026-07-23

Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.

49 MW
2026-10-31

Building 2 (AKA CB4) is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB4 was expected to be energized by Q3 2026.

245 MW
2027-03-31 (projected)

Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) that CB5 was expected to be energized by Q4 2026. However, based on the pace of Building 2, and comparisons to other projects like Stargate Abilene, we think this is optimistic. We expect a 3-month delay past the end of Q4 2026 to get to full operational capacity.

441 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.