Barber Lake site, Texas

Anthropic Barber Lake

Under construction checked 1 Nov 2026

0power online now
300 MWpeak planned or projected
n/aestimated capital cost, built so far
TXTexas

Facts

Owner
Cipher Mining
Main user
Anthropic

Timeline

2025-09-18

Site grading and civil works begin.

2025-11-29

Foundations of Building 1 are visible.

2026-07-30

Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.

2026-12-30 (projected)

Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). We estimate ~Dec 2026, about 3 months later than the disclosed target, because the site is shell-complete but not yet energized as of the Jul 2026 image. Disclosed target: [Cipher 2025-09-25 PR](https://www.globenewswire.com/news-release/2025/09/25/3156107/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html) states the 168 MW critical IT load is "expected to be delivered by September 2026."

244 MW
2027-04-30 (projected)

Building 1 Phase II is operational: 207 MW total critical IT (300 MW gross). Phase II adds 39 MW critical IT (see [Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2025/11/20/3191801/0/en/Cipher-Mining-Signs-Additional-56-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html)). We estimate ~Apr 2027, about 3 months later than the ~Q1 2027 target, based on construction progress.

300 MW

Past entries are observations; entries marked projected are estimates and can change.

Data: Epoch AI, AI data centers dataset, licensed CC BY 4.0. We selected fields, cleaned location names, and added the status label.