Amazon Madison Mega Site
Operating, expanding checked 1 Nov 2026
Facts
- Owner
- Amazon
- Main user
- Anthropic
- Project
- Project Rainier
- Chips
- Trainium2
Timeline
Land clearing begins
Generators and chillers still being installed on buildings 1-5.
Buildings 1-5 are operational, based on roofs being completed 5 months ago and generators being installed by 2025-04-10.
341 MWConfirmation that five buildings are fully equipped with cooling and backup generators.
341 MWBuildings 6 and 7 roof completed. Building 8 roof nearly completed. Building 9 roof half way up. No new operational buildings.
341 MWBuildings 6 and 7 operational, estimated from roofs having been completed 9 months ago (similar timeline to AWS buildings at New Carlisle in 2025).
478 MWBuildings 8-12 are operational. In June of 2026 only a faint outline of buildings 10,11 and 12 is visible, estimating construction completion to be the end of 2027, alligning with [expected completion by 2027](https://www.datacenterdynamics.com/en/news/aws-confirmed-as-company-behind-10bn-mississippi-data-center-development/). This final estimates adds three months to that for server installation.
819 MWPast entries are observations; entries marked projected are estimates and can change.